A homes foundation is potentially the most crucial component.
|
Slab & concrete wall construction.
|
Slab plumbing installed, slab poured & finished, concrete walls poured solid. Home is ready for framing.
|
Basement walls frame, floor trusses set, floor sheathing installed. Home is ready for log delivery.
|
6″x8″ D-profile logs delivered to site.
|
6″x8″ D-profile logs are individual cut & notched.
|
Logs are secured using 2 continuous beads of construction adhesive along with ½ dia. Stainless steel lag bolts with washers.
|
Log walls constructed.
|
Log walls constructed.
|
Loft system installed. Loft beams installed and 2″x6″ Tongue & Groove flooring is installed.
|
Large 10″x12″ beams are notched to fit on-site to ensure tight construction.
|
Gable wall framing and roof framing is completed. Home is ready for shingles, exterior windows/doors, log siding, & trim.
|
Interior view of gable framing and roof framing.
|
Deck construction.
|
Shingles installed.
|
Exterior trim is completed and exterior is stained.
|
Drywall is hung and finished on the interior.
|
Log railing is assembled and installed to provide a true log home feel.
|
Tennessee field stone is dry-stacked on the exterior masonry.
|
A well designed and properly located home blends into the natural surroundings.
|
|
|